PIR Reduction in strategy 40

$
0
0

SAP help says strategy 40 will have both PIR consumption (when SO created) and reduction (when goods issued to SO)

 

40.gif

 

but in planning strategy standard configuration req. reduction indicator is unchecked (right side bottom corner)

 

40.PNG

if req reduct.indicator is unchecked, how is sap help saying that requirement reduction happens in 40?  are these both different settings?

 