Hi Ajay,
Thanks alot on your reply.
1 may i know if i not run ck40n but just update standard price, all the scenario mentioned above still can get the cost?
2 notice in current tab in costing2 view, there are planned price and standard price.
for ck40n, it is updating planned price which in turn update standard price.
so just wonder, all the scenario above, refer to standard or planned? meaning if without planned price but just update standard price, above all scenario (pgi, backflush, pgr, etc)
Thanks alot