Re: change cost component split from deactive to active

$
0
0

Hi Szymon,

 

I read SAP information:

If you are already using the material ledger and want to use the actual

cost component split, set the indicator for activation of the actual

cost component split. Then, execute the report "MLCCS_STARTUP" that

creates the data for the actual cost component split.

 

If i want to implement activating CCS for inactive plants from 2014/07/01. I list steps here:

1. Change configure: Activate plants for actual CCS at 2014/06/30.

2. Execute report "MLCCS_STARTUP"

3. Calculate standard cost estimate for materials which were not active for actual CCS with costing date from  2014/07/01 and also release the standard price from 2014/07/01.

 

 

The above steps are enough or anything wrong? What do you see?

 

Thanks and best regards,

Jessie.